Description of the implementation

sdr
dav
dav
dav
sdr dav dav dav

Scope of works:

  • General construction works,
  • Steel structure assembly works,
  • Road works: squares, parking lots, exits,
  • Electrical installation works, including low-voltage,
  • Sanitary installation works: mechanical ventilation, water and sewage, central heating,
  • rainwater and sanitary sewage system,
  • Delivery and assembly of sports equipment,
  • Installation and commissioning of a multimedia system in classrooms and gyms.

Commencement of works: January 2017
Completion of works: February 2018
Object volume: 12 226,00 m3
Usable floor area: 1 582,40 m2
Investor: Krosno Town Hall
General contractor: PBU HAND-BUD Sp z o.o.