Warehouse Building Trans Południe in Podgrodzie

Description of the implementation






		
default
default
default
default
default
default
default default default default default default

Construction of a warehouse building with a social part along with installations, a maneuvering area and a retaining wall

Scope of works:
– Construction of foundations,
– Construction of sanitary sewage system,
– Construction of a storm sewage system,
– Construction of a steel structure,
– Installation of walls from sandwich panels,
– Construction of a “green roof”,
– Execution of electrical installation,
– Construction of an industrial floor,
– Construction of squares from concrete cubes,
– Finishing works.

Commencement of works: Novemver 2022

Completion of works: May 2023

Object volume: 42 237,10 m3

Usable floor area: 4 643,04 m2

Investor: Trans Południe Sp. z o.o.

General contractor: PBU HAND-BUD Sp. z o.o.