Scope of works:
– Foundation works,
– Steel structure assembly Works,
– Installation of external walls made of sandwich panels,
– Implementation of a seamless industrial floor,
– Road works, squares and parking lots,
– Installation works: electrical, water and sewage, gas, central heating installations,
– Installation works: ventilation and air conditioning,
– Installation of the smoke exhaust system,
– Rainwater and sanitary sewage system with pumping station,
– Construction of a tank for fire fighting purposes.
Commencement of works: September 2020
Completion of works: June 2021
Object volume: 73 687,63 m3
Usable floor area: 6 485,19 m2
Investor: Trans Południe Sp. z o.o.
General contractor: PBU HAND-BUD Sp. z o.o.