Construction of the building of the Religious House of the Congregation of Sisters Servants of the BDNP with the following functions: residential, care and medical, day care home, chapel and garage along with technical infrastructure
Scope of works:
– Demolition works of the old building of the Monastic House,
– Construction of foundations,
– Masonry and reinforced concrete works, ceiling construction,
– Construction of the roof truss and sheathing,
– Installation of external joinery,
– Installation works: electrical installations, water and sewage, central heating,
– Installation works: ventilation and air conditioning,
– Low-current installations,
– Finishing works,
– Sanitary and storm sewage system with an underground tank,
– Road works, squares and parking lots,
– Development of the area around the building.
Commencement of works: May 2022
Completion of works: March 2024
Object volume: 17 113,93 m3
Usable floor area: 2 805,26 m2
Investor: Congregation of Sisters Servants of BDNP
General contractor: PBU HAND-BUD Sp. z o.o.